U.S. Supreme Court takes up fight over .5 billion natural gas pipeline

WASHINGTON (Reuters) - The U.S. Supreme Court on Friday agreed to hear an appeal by Dominion Energy Inc and President Donald Trump’s administration of a lower court ruling that halted construction on a $7.5 billion natural gas pipeline due to run underneath a section of the popular Appalachian Trail in rural Vi

rginia. FILE PHOTO:

The U.S. Supreme Court is seen in Washington, U.S., June 11, 2018. REUTERS/Erin Schaff/File PhotoThe administration and companies involved in the project have asked the justices to overturn a ruling that found that the U.S. Forest Service lacked the authority to grant a right of way for the pipeline. Environmental groups had sued to stop the pipeline after the Forest Service gave the green light for the project through protected National Park Service land. The December 2018 ruling by the Richmond, Virginia-based 4th U.S. Circuit Court of Appeals put a stop to construction of the 600-mile (965-km) Atlantic Coast Pipeline, intended to run from West Virginia to North Carolina. Dominion Energy leads a consortium of companies in the project that also includes Duke Energy Corp. At issue is the Forest Service’s decision to allow the pipeline to cross underneath the 2,

200-mile (3,500 km) long Appalachian Trail - a popular hiking route in the eastern United States stretching from Georgia to Maine - in the George Washington National Forest. “The 2020第80期什么生肖 Supreme Court’s acceptance of our petition is a very encouraging sign and provide

s a clear path forward to resolve this important issue, said Aaron Ruby, a Dominion spokesman. A ruling is due by the end of the court’s new term,

which starts on Monday and

ends in June. The Supreme Court’s eventual ruling may also affect the proposed 300-mile (480-km) Mountain Valley Pipeline, which is intended to run from West Virginia to southern Virginia and crosses the trail in the Jefferson National Forest. ‘COSTLY AND UNNECESSARY’ After a lengthy application process involving multiple federal agencies, the Forest Service granted the consortium a right of way under th

e trail in January 2018, prompting environmental groups to file a lawsuit. “Th

e Atlantic Coast Pipeline is a dangerous, costly and unnecessary project and we won’t stand by while Duke and Dominion Energy try to force it on our public lands, threatening people’s health, endangered species, iconic landscapes and clean water along the way, the Sierra Club and Southern Environmental Law Center, two of the environme

ntal gr

oups challenging the pipeline, said in a joint statement. The 4th Circuit ruled that the Forest Service did not have the power to grant a right of way under a federal law c

alled the Mineral Leasing Act.

The court cited a section of the law that says federal agencies can grant rights of way for pipelines on “federal lands but specifically excludes land that is part of the federal National Park system like the Appalachian Trail. The Trump administration disputed that interpretation, with Solicitor General Noel Francisco saying in court filings that the National Park Service has only limited authority to maintain the trail and that the Forest Service has the authority to approve rights of way across it. Lawyers for the pipeline consortium noted that more than 50 pipelines already cross under the trail. The 4th Circuit’s ruling has the effect of “rendering the footpath a 2,200-mile barrier separating resource-rich areas to its west from consumers to its east, the consortium said in court filings. The environmental groups have said the project could go ahead under a different route that does not cro

ss the trail on federal land. State and private landowners have the authority to grant rights of way under the trail, the groups added.